For sale 3 x solar project in Brazil

3 x solar project for sale in Brazil

1.- 2 x 90 = 180 Mw

2.- 3 x 54 = 162 Mw

3.- 1 x 90 = 90 Mw

     Total =  432 Mw

Price = USD$60,000 Per Mw of  Project

More details

J carlo

$60,000.00

3 x Solar pojects in Brasiel

1.- 2 x 90 = 180 Mw

2.- 3 x 54 = 162 Mw

3.- 1 x 90 = 90 Mw

     Total =  432 Mw

Price = USD$60,000 Per Mw of  Project

solar project for sale in Brazil
Has the connection to the electricity grid already been granted?

Answer: We have the connection studies and access information of ONS - Operator of the National Electric System, favorable to the connection.
HAS PREVIOUS ENVIRONMENTAL LICENSE, REGISTRATION IN ANEEL, PREFERRED LICENSE AND REGISTRATION IN CREA
• Network access guarantee (in the last auctions, in RN where the projects you pass me are located, the Joao Camara substation, has received several projects and it may be that the connection of these PV plants can be compromised) DRO (ANEEL grant requirement)
• Finally, what is the possibility of getting the LI (installation license)?
IN A TERM OF 4-6 MONTHS
Below are our considerations regarding the questions below:


 - At this time, at what stage are the projects detailed?


Answer: The projects have more than 02 years of solarimetric measurement, have the data duly certified and with production calculation, have DRO ANEEL - Grant request from the National Electricity Agency, have a survey, conduct studies, survey topography (planimetric and planimetric), steady-state connection studies (load flow and short circuit), civil and electrical executive projects of power plants, including medium voltage network, elevator substation, transmission line, connection bay, road and access projects inert to the plant, environmental studies, previous environmental license, registration in CREA and technical qualification by EPE - Energy Research Company.


- What permissions do you already have?
Answer: Prior environmental license, ANEEL registration, city council license, CREA registration.


- Which ones are missing?
Answer: Installation license, plant suppression and IPHAN: estimated time limit for the issuance of 4 to 6 months.


- Have you already been granted the connection to the power grid?

Answer: We have the connection studies and access information of ONS - Operator of the National Electric System, favorable to the connection.


- What is the sales price of the kWh produced?
Answer: The energy produced by the solar plant can be marketed at federal government auctions or in the free energy market.
In the last auction, held on 18-10-19, MWh R $ 84.50 was negotiated
 (USD $ 22) (20 years).
Through the free market we have a marketing proposal for the amount of energy sold around R $ 205.00 (USD $ 50.95) per MWh (20 years).

Write your review

For sale  3 x solar project in Brazil

For sale 3 x solar project in Brazil

3 x solar project for sale in Brazil

1.- 2 x 90 = 180 Mw

2.- 3 x 54 = 162 Mw

3.- 1 x 90 = 90 Mw

     Total =  432 Mw

Price = USD$60,000 Per Mw of  Project

Write your review